Abatement in construction
Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect. Abatement only applies to payment for labour and materials, not to professional services or to losses resulting from delay or disruption. Abatement exists as a common law right.
Abatement is often confused with set off. Set off (or contra charging) requires that a breach of contract can be demonstrated. It can permit the withholding or extinguishing of an agreed payment. Set off can be used to recover the costs of rectifying defects and any delay. Whilst set off is often accompanied by a counterclaim it is to be distinguished in that set off cannot, unlike a counterclaim, give rise to a positive balance of claim. Set off rights can either be contractual, equitable or in the case of insolvency, statutory.
Before the 2011 amendments to the Housing Grants Construction and Regeneration Act, set off and counterclaim were only permitted if a withholding notice was issued, whilst abatement did not require a withholding notice as the value of the works had been reduced and there was only an obligation to pay the amount properly due.
Since 2011 however, set off, counterclaim and abatement all require that a pay less notice is issued.
[edit] Related articles on Designing Buildings
Featured articles and news
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
Comments
Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect.